Foundation work continues at the Biocentre site within the Albertov Campus. By the end of September, the construction team had drilled 156 foundation piles and completed 12 geothermal boreholes. These have already undergone outfitting — the installation of necessary pipes and reinforcement — as well as pressure grouting to ensure their strength and long-term functionality. A total of 48 boreholes will be installed.
30 September 2025
Drilling of the piles that will form the structural foundation of the entire building is continuing at the Biocentre construction site in the Albertov Campus.
24 September 2025
The construction of the Biocentre is moving forward with the start of geothermal drilling.
10 September 2025
Construction activity has resumed at the Biocentre building site on the Charles University Albertov Campus. Following the completion of rescue archaeological research, the contractor has started work on the foundations of the building.
27 August 2025
Rescue archaeological research at the Biocentre construction site on the Charles University Albertov Campus has been successfully completed.
30 June 2025
Archaeological excavation at the construction site continues
21 August 2024
Watch the construction of the Biocentre in real-time online stream
9 July 2024
Construction of the Biocentre building has started
4 April 2024
Decision and notice on the selection of the construction contractor – Biocentre
7 February 2024
Biocentre is financially supported by the National Restoration Plan; Investment identification number: Z332802000005.